Rise Carr

▐  2.5 MW / 5 MWh GSS®

3_Rise Carr -retouched w logo (5x7)

▐  T&D Support Pilot

▐  2.5 MW Power Capability

▐  5 MWh Energy Capacity

▐  Two Battery Containers with Integrated Cooling

▐  One Inverter Container

▐  Installed at the Rise Carr substation

▐  Commissioned December 2013


 Harrowgate Hill

Harrowgate Hill 1

▐  T&D Support Pilot

▐  One LD Rack

▐  One 50 kW / kVA inverter with integrated isolation transformer

▐  One AEROS® Control Rack

▐  Installed in a pre-existing building at the Harrowgate Hill substation

▐  Commissioned December 2013


 High Northgate

▐  T&D Support PilotHigh Northgate

▐  Two LD Racks

▐  One 100kW/kVA inverter with integral isolation transformer

▐  One AEROS® Control Rack

▐  Installed inside a custom container with integral cooling at the High Northgate substation

▐  One AEROSTM Control Rack

▐  Installed in a pre-existing building at the Harrowgate Hill substation

▐  Commissioned December 2013


 